![]() To me task B start should move but it stays the same. I change the duration of task A from 5 to 10days because it is taking longer than expected. ![]() So as an example, I have task A (create project plan) and task B (signoff project plan) is FS+1day I started my project fresh (didn't try to reuse an old project with old info, just started typing tasks and linking them fresh) My project is standalone (no related projects linked) I went into file options schedule and calculate project after each edit is on I have not entered start or end date manually on any of them I just got project 2010 at work and for some reason none of the tasks are changing based on the predecessors unless I delete the start and end date and the predecessor info and then retype the predecessor info. OK, I know this has been asked a bunch of times but I can't find a recent one and I have tried the suggestions with no luck.